Needham Massachusetts Parks and Recreation Homepage
Search

Walker Pond Improvements Project

Walker Pond with overgrowth_ESS Group_2017

Walker Pond has the potential to support boating and fishing as well as skating in the winter months, but due to nutrient and sediment loading from the pond’s watershed, the waterbody has significantly deteriorated in recent years. The primary recreational uses of the pond have been fishing, skating, bird watching, and quiet contemplation.

Walker Pond is choked with excessive aquatic vegetation that needs to be removed for the health of the pond. A three-phase capital improvement project was proposed and approved by the Select Board in 2021.

A Phased Project Strategy

The Walker Pond Improvement Project is a multi-phased project broken into three (3) categories of activities to address the water quality of Walker Pond.

Category IAnalysis of the contributary area providing runoff to the pond. The analysis will help the design team develop the improvement plan. Nature based solutions will be installed to encourage infiltration and promote nutrient uptake and soil activity resulting in stormwater quality improvements. Sediment and litter removal will be increased with the installation of drainage manholes and sumps. Public education and participation via pamphlets and media, catch basin disk placement, and educational signage will support the continued improvement of water quality.
Category IIAssessment of treatment options for waterbody conditions. A report conducted by ESS Group, Inc. in 2017 provided recommendations to improve the health of the pond. Conservation has endorsed hydro raking, the mechanical removal of vegetative overgrowth and will consider the application of chemicals, herbicides, and algicides to the pond if deemed necessary. Improvements to the outlet structure, including the overflow grate and wooden stop-log replacements will be assessed.
Category IIIInvolves the extension of the sewer main in Walker Lane. Although not specifically a part of the Walker Pond Capital Improvement Project, the extension of the sewer main would allow additional properties abutting the pond to redirect their sewage flow from entering septic system and leach fields in the ground and directing it toward the sewer main where it is treated at the sewer treatment plant prior to discharge.


Walker Pond Update July 2022Walker Pond Update October 2022

Walker Pond Update January 2023Walker Pond Update July 2023Walker Pond Update November 2023

Walker Pond Update February 2024, Walker Pond Update July 2024


  1. Category I
  2. Category II
  3. Category III

Final plan design was achieved March 28, 2022. The design involves the reduction of impervious pavement and the addition of stormwater treatment through landscape filter strips and infiltration trenches.

Walker Pond improvements plan_2022

Educational signage has been incorporated into the final design. The messaging will be customized to educate visitors about Walker Pond wildlife, effects of pollution and mitigation practices.

Educational Signage

The addition of two Leaching Manhole structures is part of the design to facilitate inspections of the stormwater system as well as maintenance of the stormwater line.

  • Reduction of Total Suspended solids into Walker Pond.
  • Reduction of weed growing nutrients such as Phosphorous into Walker Pond

09232022_Walker Pond Improvements_Cat1_Installation of leeching manhole structure

BMPs are included in the design to help replicate or restore the natural replenishment of groundwater via infiltration. By reducing the volume of runoff, as the result of impervious cover, leaving specific properties through infiltration, pathogens and phosphorus (and nitrogen) are reduced from direct discharges into nearby waterbodies. 

Walker Pond Filter Strip Photo provided by Walker Pond Association member

  1. Needham Massachusetts Homepage

Contact Us

  1. Department of Public Works

    Public Services Administration Building
    500 Dedham Avenue
    Needham, MA 02492
    Phone: 781-455-7550
    Email Department of Public Works

Government Websites by CivicPlus®
Arrow Left Arrow Right
Slideshow Left Arrow Slideshow Right Arrow